Wollongong City Council are giving our surf club building a birthday!
They are:
1) Replacing the roof sheeting, fascia, eave linings, gutters & down-pipes
2) Removing existing paintwork, re-rendering & repainting
3) Patching any exposed concrete reinforcing
4) Replacing lintels over all doorways & windows
5) Installing a concrete mowing strip around the entire building
6) Installing cladding & flashing to gym to waterproof this part of the building
7) Installing a new stainless steel door jamb & doors on the front door
Works are due to start shortly after Anzac Day 2015 & will take around 4-5 months. Access to sections of the club will be restricted during the project.